Skip to content

Data Centre ​

The Data Centre app watches a data hall or server room the way the person who runs it would. It opens on one sentence — what needs someone now, or Everything is normal and what was checked — then how efficiently the site uses power (PUE), how warm the air going into every rack is, whether the UPS units, cooling and generator are doing their job, and what it is all costing. Alerts open, escalate and clear on their own, and repeats are grouped into the cause behind them. A wall screen puts it all on the control-room TV, in 2D or 3D. It is for the people who answer for uptime: the operations lead, the facilities manager and the on-site engineers.

The Data Centre Now page for Northwind Data Hall: Everything is normal — all 42 racks are below 27 °C, power is on mains, every cooling unit is running. Four key numbers: PUE 1.39, under target 1.45, on a scale from 1.0 to 2.0 marked at the target and the old 1.68; IT load 198 kW, 58 % of 340 kW designed, room for 142 kW more; Power on mains, 42 min on battery, 4 UPS at 34–54 % load, generator ready; Cooling all running, 17.2 °C supply air, 6 of 6 units, fan wall 12 of 12 fans. Below, Every rack: the Main Hall's rows A to D and the AI Pod's rows G and H, each tile showing its inlet temperature in green, with Inlet air, Power and % of rated buttons; on the right, Click a rack to see its last 24 hours and This month — energy cost RM 37,671, saved against PUE 1.68 RM 6,371, practice checks met 11 of 17.
Northwind Data Hall right now: nothing needs anyone, then every rack where it stands

Who uses it ​

Ravi Kumar — Operations LeadRaviOperations LeadAisha Rahman — Facilities ManagerAishaFacilities Manager
RoleWhat they do with the appAt Northwind Tower
Operations leadWatches Now, takes alerts with I'm on it, reads Energy and the practice review, decides what to fix firstRavi Kumar
Facilities managerOwns the site's limits, tariff and targets in Setup, and who is told about alertsAisha Rahman
On-site engineer or technicianUses the Floor to find the rack or unit an alert names, puts a unit into maintenance before working on itA cooling or UPS contractor, given the app for the visit
Control roomKeeps the wall screen up on a TVThe NOC, the security office
Whoever answers for uptime and costReads Energy, the Power page and the operating-practice reviewRavi reports them to management

Everyone with the app sees every page except Setup. Setup, and moving racks on the Floor, need configure rights on the app. At Northwind both Ravi and Aisha have them.

A day at Northwind Tower ​

Northwind Tower's data hall is in the basement: a Main Hall of 32 racks (rows A–D) and an AI Pod of 10 high-density racks (rows G and H), fed by four UPS units, cooled by four CRAC units, two in-row coolers and an 8-metre fan wall, with a standby generator in the yard. An edge gateway reads all of it and sends the readings to Omaya every minute.

TimeWhat happensHow
08:30Ravi Kumar — Operations Lead Ravi opens Now: Everything is normal, PUE 1.39, about 200 kW of IT load.Read Now
09:27Ravi Kumar — Operations Lead Rack A08 in the Main Hall passes the hall's 27 °C limit. One warning opens, Main Hall: A08 inlet 27.1 °C, and is pushed to everyone with the app. Now turns amber: Opened 1 min ago. Nobody has taken it yet. It has happened 28 times in the last 7 days. Ravi taps I'm on it.Deal with an alert
09:42A08 has been back below the limit for ten minutes: the alert clears itself.Deal with an alert
09:45Ravi Kumar — Operations Lead On Alerts, What keeps happening shows A08 runs warm 4 times a day — at about 03:30, 09:30, 15:30 and 21:30, while its neighbours stay at 22 °C. A schedule is behind it, not the room. Ravi taps Make a work order for the cooling contractor.What keeps happening
10:17The mains dips for three minutes. All four UPS carry the racks on battery; the generator starts and takes the load. Power lists it under Every time it went on battery and notes the dips come every 4 days at about 10:17.Read the Power page
All dayIn the security office, the wall screen shows the same sentence, the key numbers and every rack, turning slowly in 3D.The wall screen
14:00Ravi Kumar — Operations Lead Ravi opens Practice: 11 of 17 practices met. He presses Ask OAIA for a review.Review operating practice
16:00Ravi Kumar — Operations Lead For the monthly review Ravi opens Energy: PUE down from the 1.68 baseline, and the saving in ringgit.Read energy and cost

How to read Now ​

Open Data Centre; it opens on Now (What needs you, every rack). The page refreshes itself every 30 seconds; the chip at the top right says how old the readings are (Readings 32s ago).

The sentence at the top says what needs someone first:

It saysWhen
(UPS) on battery: … minutes left (red)A UPS is running on battery, with whether the generator is running
The alert's title (red or amber)An alert is open: how long ago, who is on it or Nobody has taken it yet, how often it happened in the last 7 days, and how many more are open. Show A08 picks the rack below; I'm on it takes the alert
(Unit) has stopped reporting (amber)A UPS, cooling unit or fan wall has gone quiet, so nothing on the page can vouch for it
Everything is normal (green)And what was checked: how many racks are below the warning limit, power on mains, every cooling unit running

The four key numbers:

CardWhat it tells you
PUETotal facility power ÷ IT power, lower is better. The bar runs from 1.0 to 2.0 with your target and where you started (was) marked, and the verdict beside the number: under target, above target, or worse than before. A note appears if facility power is estimated or not every meter is reporting
IT loadIT power now against the halls' design load, how much room is left, and the busier hall
PowerMains or On battery: minutes the batteries would last (or have left), the UPS load range, and whether the generator is ready. Power path → opens the Power page
CoolingAverage supply air, how many units are running (and which have stopped), the fan wall's fans, and the power used to cool

Every rack is one tile per rack, laid out row by row as the racks stand. Choose what the colour shows:

  • Inlet air — the temperature of the air going into the rack. Green is in range, amber is warm (past the hall's warning limit), red is critical, blue is colder than needed (wasted cooling), grey is a sensor that has stopped reporting.
  • Power — what each rack draws, against the busiest rack.
  • % of rated — each rack's power against its rating: amber from 80 %, red from 90 %. Racks with no rating show grey.

Your choice is remembered. Click a rack to see, on the right, its inlet air and power now, its last 24 hours of inlet air against the warning line, and what to do about it — warmer than the racks beside it, so the cause is local, the whole row is warm, close to its rated power, or inside every limit. Show on the floor opens it on the Floor.

Every rack with rack A08 selected, and on the right its panel: Rack A08, Main Hall, row A; inlet air now and its range over 24 hours; power and its share of the rated kW; a line of the last 24 hours of inlet air under the dashed 27 °C warning line, with four short climbs a day; a note on what to do; and a Show on the floor button.
A08's last 24 hours: four short warm spells a day
Every rack coloured by % of rated: most Main Hall racks pale, a few in light indigo between 60 and 80 %, and several AI Pod racks amber and red at 80 to 95 % of their rating, each tile showing its percentage.
The same racks by % of rated: the AI Pod is close to its circuits

This month gives the energy cost so far, the saving against your starting PUE and how many practice checks are met.

How to deal with an alert ​

You hear about an alert three ways: a push notification to everyone who has the app, an email if your Setup sends one, and the Alerts tab, whose hint always says how many are open (1 open now). The top of Now and the wall screen show it too.

  1. Open Alerts. Under Open now, each alert has its level, hall, when it opened and who is on it.
  2. Tap I'm on it to tell the team you have it. Your name appears on the alert, on Now and on the wall screen. It does not close the alert.
  3. Show rack (or Show unit) opens the Floor with it picked, so you know where to walk to.
  4. Fix the cause. The alert clears on its own once the reading has stayed back in range for the settle time (10 minutes at Northwind); the line under it says when it will close and when it would escalate.

If critical alerts would reach nobody by email, a red line at the top of the page says so, with Add who is on call for people who can change Setup.

The Alerts page: 126 alerts in 30 days came from 3 causes. A red line: Critical alerts reach nobody by email, Add who is on call. Open now: nothing is open. What keeps happening: three cards with a 24-hour strip each — Mains dips every 4 days (8 critical, at about 10:17 for about 5 minutes; the UPS carried the racks and the generator started; ask the utility about switching on the feeder), A08 runs warm 4 times a day (108 times, at about 03:28, 09:27, 15:27 and 21:29 for about 15 minutes; its neighbours stay at about 22 °C; a schedule is behind it), and Fan wall FW-01: a fan stops every 3 days (10 times, at about 14:00 for about 1 h 32 min). Each card has Make a work order and See all buttons.
126 alerts, three causes

What keeps happening ​

Most alerts in a data hall are the same thing again. Alerts groups every alert of the last 30 days by what it was about — the same rack running warm, the same mains dip, the same fan wall — and shows each group that happened three times or more as one card:

  • how often (every day at about 03:30, 09:30, 15:30 and 21:30, every 4 days at about 10:17, or irregular), for how long, and a strip of the hours of the day it happens;
  • for a warm rack, whether its neighbours stayed cool — a rack alone means a local cause (blanking panels, a floor tile, a job on its servers);
  • whether anyone acknowledged any of them;
  • Make a work order (when your organisation has the Facility app) opens a job with the facts in it, at high priority for a critical pattern. If one is already open for that pattern, the button opens it instead;
  • See all shows just that pattern's alerts in the list below.

Every alert lists the last 30 days: what, level, when, how long it lasted and who took it. Show narrows it to Critical only, Not acknowledged, or one pattern; a repeat says repeat. Show more pages through the rest.

How alerts behave, so you can trust them:

  • One alert per subject. A warm hall is one alert named after its warmest rack, not one per rack. The name follows the warmest rack if it changes.
  • They escalate on their own. A warning becomes critical when the rack passes the critical limit, or when it is still climbing (by 1.5 °C in 10 minutes at Northwind) ten minutes after it opened.
  • They never step down while open, and a value hovering on the line is not a recovery: it has to settle half a degree below the limit.
  • Silence is not recovery. If a unit stops reporting, its open alerts stay open and it gets a not reporting alert of its own.
  • People are not flooded. Each alert is sent once per level. A critical alert nobody has acknowledged after 15 minutes is sent once more. A critical alert that clears sends an all-clear.
AlertRaised when
Hall: rack inlet … °CThe warmest rack's inlet air is past the hall's warning (or critical) limit
Hall: no inlet readingsNone of a hall's rack sensors is reporting
UPS on batteryA UPS is running on battery (always critical)
UPS battery at … % on mainsBack on mains but the battery is below the warning level: the next outage has less runtime
UPS load … %A UPS is loaded past its warning level
Unit stoppedA cooling unit or fan wall on duty has stopped (critical if its hall is already warm)
Unit supplying … °CA cooling unit or fan wall is blowing air warmer than the supply-air limit
Fan wall: … of … fans failedOne failed fan is a warning; a quarter of the wall (at least 2), or any while the hall is warm, is critical
Unit: not reportingA UPS, cooling unit, fan wall or generator has gone quiet
On battery … min — no generator runningA UPS has been on battery for 90 seconds and no generator is running

How to find a rack or unit on the Floor ​

  1. Open Floor. It shows the floor with each hall's racks and every UPS (U), cooling unit (C), fan wall (F) and generator (G) where it actually stands, on a dark plan so the colours read well.
  2. Choose Whole floor or one hall to zoom in, and what the colour shows: Inlet air, Power or % of rated — the same choices as on Now. The number on each rack follows your choice.
  3. Type a name in Find a rack or unit (A08, UPS B1) to jump to it, or click one. The panel on the right shows its readings in words and what to do; for a rack, Open its history shows its last 24 hours on Now.
  4. Press 3D for a model of the floor you can turn (drag), zoom (scroll) and move (right-drag). The colour choice and clicking work in 3D too.
The Floor of Basement — Data Hall in 2D on a dark plan: the Main Hall's four rows of green racks with cooling units down the side, the Electrical Room with four UPS units, the AI Pod with two rows and the fan wall along its end wall, and the other rooms outlined. Inlet air is chosen, A08 has been found with the search box, and the panel on the right shows Rack A08, Main Hall, row A, its inlet air, humidity, power against its rating, state and an Open its history link.
Finding A08: type its name, and the Floor picks it
The same floor in 3D: green rack rows in the Main Hall and AI Pod, blue cooling units labelled CRAC-01 to CRAC-04, IRC-01 and IRC-02, four UPS units in the Electrical Room and the tall fan wall FW-01 along the AI Pod's end wall.
The 3D view

A unit with an open alert takes on the alert's colour, and the rack a hall alert names turns red, so the Floor shows you where to walk to.

Moving racks (configure rights only): press Arrange, drag a rack or unit to where it really stands, and double-click a rack or fan wall to turn it. Racks not yet on the floor wait in a tray at the edge (Not placed yet). Press Done when finished.

The wall screen ​

Wall screen (at the top of Now and Floor) opens a full-screen page for the control-room TV: always dark, sized for a 16:9 screen from 1280 × 720 to 4K, and readable from the back of the room. It shows:

  • the site and floor, the date and a large clock in your organisation's time zone;
  • the same sentence as Now — the worst open alert, how long it has been open and whether anyone took it, coloured by level — or Everything is normal;
  • PUE against its target, IT load against capacity, and Power: On mains with the battery minutes, or On battery: … min left in red;
  • every rack's inlet air, hall by hall, row by row, warm racks ringed;
  • along the bottom: cooling units running and supply air, the fan wall, the generator, and when it last updated.

Choose 2D or 3D at the top left (the controls and the mouse pointer hide after a few seconds still). In 3D the room turns slowly by itself and pauses while someone drags it. Add to the address:

AddEffect
?view=3dOpen in 3D
?cycle=60Switch between 2D and 3D every 60 seconds (20 at the least)
?floor=…Another floor, for a site on several floors

The screen updates every 30 seconds and keeps the TV awake. If it cannot reach Omaya it says Not updated for … min in amber; if the person it was opened as is signed out, it says so — sign in again on that screen. It needs someone with the app signed in; for a lobby screen with no sign-in, use the Data hall widget in TV Dashboard.

The wall screen at 1920 by 1080: Northwind Data Hall, Basement — Data Hall, Monday 12 October, 23:34. A green band: Everything is normal — 42 of 42 racks in range, 6 of 6 cooling units running, on mains. On the left, PUE 1.39 target 1.45, IT load 198 kW 58 % of 340 kW, Power on mains, 42 min on battery, 4 UPS. On the right, Rack inlet air: the Main Hall's rows A to D and the AI Pod's rows G and H as large green tiles with their temperatures. Along the bottom: cooling 6 of 6 running at 17.2 °C supply, fan wall 12 of 12 fans, generator ready, updated 23:34:36.
The wall screen in 2D
The same wall screen in 3D: the rack inlet panel now shows the whole floor as a 3D model turning slowly — the Main Hall's green rack rows with the CRAC units, the UPS units in the Electrical Room, the AI Pod with its in-row coolers and fan wall, and the generator in the yard.
…and in 3D, turning slowly

How to read the Power page ​

Open Power (Mains to rack, batteries). One sentence says where you stand: On mains. If mains fails now, the batteries hold the racks for 42 minutes; the generator should take over — or, in red, which UPS is on battery and for how long.

The power path runs left to right: Mains (the site's power now, Steady or lost) and the Generator (Ready or Running, when it last ran, and a warning when it has had no 30-minute test run in the last month) → the Transfer switch (on mains or on the generator) → each UPS, grouped by side A and B, with its load against its rating, battery, minutes on battery and a 24-hour load line → the Racks' IT load, per hall. On a narrow screen the path scrolls sideways.

If one side fails works out, for each side, what the other side would have to carry: today's IT load against that side's total UPS rating, with an 80 % guide line. It says plainly whether the site stays up, how much margin is left, and how much load you could add before one side alone would pass 80 %. The UPS sides are set in Setup → Devices; until they are, the card says how.

Every time it went on battery lists the last 30 days, one row per mains dip however many UPS went on battery: when, how long, the lowest battery, whether the generator started and after how long, and Handled, Batteries ran low or Still on battery. When the dips keep coming at the same time of day, a line says so — at Northwind every 4 days at about 10:17: ask the utility whether there is switching on the feeder at that time.

The Power page: On mains. If mains fails now, the batteries hold the racks for 42 minutes; the generator should take over. The power path: Mains 276 kW steady; Generator ready, not running, last run yesterday, no 30-minute test run in the last month; Transfer switch on mains; UPS A1 and A2 on side A at 34 % load, B1 and B2 on side B at 54 %, all on mains with batteries at 100 % and 42 minutes; Racks 198 kW IT, Main Hall 68 kW and AI Pod 131 kW. If one side fails: with side B off, side A carries all 198 kW, 99 % of its 200 kW — over the 80 % guide, the site stays up with little margin. Every time it went on battery: mains dips of 3 minutes every few days at 10:17, each handled, the generator starting within about a minute.
Northwind on mains, and what would happen if one side failed

Read it the way an auditor will: every dip should show the generator starting if it was long enough to matter. If a UPS was on battery for more than 90 seconds and no generator ran, that was a critical alert at the time.

How to read energy and cost ​

  1. Open Energy (PUE, energy, cost, reports); it opens on Energy and PUE.
  2. Choose 7 days, 30 days or 90 days.
  3. The cards give the period's PUE, Facility energy (with IT energy and peak IT load), Energy cost at your tariff, and Saved vs baseline.
  4. Power usage effectiveness, daily plots each day's PUE against your baseline and target.
  5. Daily energy splits each day's kWh into IT, cooling and other. Point at a bar for its numbers.
  6. Open Day by day for the table: Facility kWh, IT kWh, Cooling kWh, Other kWh, Peak IT kW and Cost per day. Today is marked (today, so far) and updates every five minutes.
Energy and PUE for 30 days: PUE 1.48 against baseline 1.68 and target 1.45; Facility energy 213,912 kWh, IT 144,417 kWh, peak IT 222.3 kW; Energy cost RM 96,261 at RM 0.45/kWh; Saved vs baseline RM 12,914, 28,698 kWh avoided. The daily PUE line falls from about 1.53 in early September to about 1.43 at the start of October, crossing the target line. Below, daily energy bars split into IT, cooling and other.
Northwind's month: PUE coming down to its target after the cooling tune-up

Saved vs baseline is what the same IT load would have cost at your baseline PUE, minus what it did cost. It is the number to take to a management meeting: it does not change when the IT load grows, only when the facility gets more or less efficient.

Energy for a day uses each meter's own counter when it sends one. Otherwise the app adds up its power readings over the day. A meter that stops reporting leaves a gap in the total, and the app does not fill it in.

How to review operating practice ​

Open Practice (Checks against good practice). Where the site stands shows how many of 17 practices are met, to act on, and to watch. The practices come from ASHRAE, The Green Grid, NFPA 110 and redundancy practice, and each one is checked against your site's own readings, in five areas: Thermal, Cooling & airflow, Power & resilience, Energy and Monitoring & response.

Each check reads one of:

LabelMeans
MetThe site meets it, and the line under it says by how much
WatchClose to the line, or met with a caveat
Act onNot met. Why it matters and What to do open under it
Not measuredThe site does not measure what this check needs. The app says so instead of guessing
Not applicableThe plant it is about is not registered here (no generator, no fan wall)
One check, Each hall's UPS can lose one unit (N+1 or 2N), marked Act on: Main Hall 71 kW load, 100 kW left with the largest UPS out; AI Pod 137 kW load, 120 kW left with the largest UPS out. Why it matters, What to do, and the source: Redundancy practice — Uptime Institute tiers, TIA-942, EN 50600.
A check to act on, with why it matters and what to do

Ask OAIA for a review turns the list into a plan. OAIA, the platform's AI assistant, reads the checks that are not met with your site's numbers and picks the two or three to do first, with why now and a first step for each. It takes under a minute. It only chooses from the checks on the page and does not invent figures. The review is dated (Reviewed … ago for …) and, if the checks have changed since, it says so; press Review again. You can ask once every few minutes.

Where the site stands: 12 of 17 met, 3 to act on, 2 to watch. OAIA's review: AI Pod has no UPS redundancy and seven racks above 80% load; critical alerts have no email recipient. First, each hall's UPS can lose one unit: confirm AI Pod UPS rated kW, then start moving IT load to the Main Hall this week. Second, racks run below 80% of rated power: move what you can off H03 and H05. Third, critical alerts reach someone: add named recipients this week. Reviewed 1m ago for Ravi Kumar, with a Review again button.
Ravi's review at 14:00: what to do first, and why

The review uses your organisation's AI allowance. If AI is switched off, or the month's allowance is used up, the page says so and the checks still apply.

The checks are a guide built from published practice, not a certification or an audit.

How to read the report ​

Energy → Report sums up any period, up to 92 days, for the whole site or one hall. CSV downloads every table, and What this report is, at the foot of the page, explains each figure.

SectionWhat it tells you
EnvironmentThe share of time each rack's inlet temperature and humidity spent in the recommended band (up to the hall's warning limit), the allowable band (up to its critical limit) and out; the worst racks, hot spots and every excursion with how long it lasted
PUEFacility energy divided by IT energy over the days that have both — never an average of daily ratios — and DCiE. When it cannot be worked out, it says why (nothing measures IT, or no site meter)
UPSTimes on battery and for how long, battery-low and other events, peak and average load; generator runs
AlertsRaised, acknowledged and still open, and how long acknowledgement took
CapacityEach hall's and rack's peak power against its rating and design load

Battery state of health and U-space used read not measured: the app does not take those readings. A period that starts before the rack sensors were fitted says from when it has readings.

With one hall picked, the UPS units and generators that Setup gives no hall, and the alerts raised for the whole site (a generator that did not start, for example), come in their own Site-wide section after Alerts: never added into the hall's figures, never left out. The other halls' units and alerts are not shown. PUE is always the whole site's.

Energy → Scheduled reports emails it for the whole site or, with a Hall picked on the schedule, for one hall with its Site-wide section (see Scheduled reports in the apps). A hall deleted after the schedule was saved sends the whole site, and says so.

Using it in your organisation ​

Corporate server room or on-site data hall ​

Setting. One or two rooms in an office building, like Northwind's: a few dozen racks, two or four UPS units, CRAC units, perhaps a generator shared with the building. Who does what. The operations lead watches Now and Alerts; the facilities manager owns limits and tariff; the cooling and UPS contractors get the app for their visits. What matters. A site meter and an IT meter (at the UPS output), so PUE is measured, not estimated. Rated kW on every UPS, so the redundancy check works. Tip. Put the email recipients in Setup on day one. The practice check Critical alerts reach someone and are acknowledged fast fails until someone outside the app is told.

Colocation provider ​

Setting. Customer racks in several halls, sold by the kilowatt. Who does what. The NOC shift keeps the wall screen up and works from Alerts around the clock; the facility manager reads Energy and Practice weekly; sales use rack load to see which customers are near their contracted power. What matters. One hall per room with its own limits. A PDU per rack, so % of rated and the 80 % check show which customers are close to their circuits. Fan walls and cooling units with their Rated kW entered. Tip. Use Maintenance mode for each unit you work on during a planned shutdown. The unit raises nothing for 8 hours, then goes back to normal on its own, so no alert is silenced for good by mistake.

University or hospital IT ​

Setting. A central data room plus smaller comms rooms on other floors or buildings, often run by a small team with no night shift. Who does what. The IT infrastructure manager receives critical alerts by email and push; estates handles cooling and power. What matters. Set Who hears about alerts to the on-call address, critical only. Give each comms room its own hall (kind Network room) with its own inlet sensor, even if it has only two racks. Tip. If a room has a cooling unit as a spare, mark it Standby in Setup. Otherwise the app assumes every unit should be running and raises stopped alerts for the spare.

Setting it up for your organisation ​

For whoever has configure rights on the app, with an administrator for the first step.

What must exist first ​

  • An edge gateway on your network that reads your meters, PDUs, UPS units and cooling units (over Modbus TCP, OPC UA or SNMP) and publishes the readings to Omaya over MQTT. It dials out; nothing connects in to your plant. An administrator creates its connection under Connectors → IoT Gateway (MQTT), vendor Generic, protocol Telemetry, and registers the gateway under Devices → Gateway. See MQTT gateways.
  • Each meter or unit registered as a device, with its own identifier.
  • The floor (venue) the halls are on, and ideally each hall's outline drawn as a zone, so the floor plan can draw it.
  • The plan that includes Data Centre (enterprise).

Checklist ​

  1. Setup → Connect your plant (How readings get here) shows the message shape the gateway must send and the reading names the app understands. Hand it to whoever configures the gateway.
  2. Setup → Halls & racks: under New hall, give each hall a Name, Kind (Colo hall, AI / high-density, Network room, Other), Floor, Outline (zone), inlet limits and Design IT load (kW), then Save hall.
  3. Add racks a row at a time: Add a row (the row letter), Racks, Starting at, Rated kW each, then Add row.
  4. Setup → Devices (Which device is which): give each device its Role, and its Hall and Rack where it has one. Sends shows the reading names each device has reported recently, so you can tell a meter from a sensor. Enter Rated kW for UPS units and cooling units, and the Side (A or B feed) for each UPS so the Power page can tell you what happens if one side fails. Press Save on each row.
  5. Setup → Site & limits: site name, currency, tariff, PUE baseline and target, alert limits, and Who hears about alerts.
  6. Open Floor → Arrange and drag racks and units to where they stand.
  7. Give the app to the people who need it, with configure rights only for those who should change Setup.
Setup, Connect your plant tab: How readings get here. An edge gateway polls the meters, PDUs, UPS units and cooling units over Modbus TCP, OPC UA or SNMP and publishes to Omaya over MQTT. Four numbered steps, then an example message with gateway_mac, timestamp and a devices list, each device with a mac and values such as kw, kwh, load_pct, battery_pct, supply_temp_c, inlet_temp_c and fan wall readings.
What to hand to whoever sets up the gateway
Setup, Devices tab: Which device is which, with a filter box. One row per device: its name, the readings it sends, its Role, Hall and Rack, Rated kW, Mode, Length m and Side — the Side box is used only for UPS units — and Save.
Giving each device its role

Roles ​

RoleWhat the app reads from it
Site meterTotal facility power and energy: the top of the PUE sum
IT load meterIT power, usually at the UPS output: the bottom of the PUE sum. Without it, the rack PDUs are added up
Cooling meterCooling power. Without it, the cooling units' own power is added up
Other load meterLighting, offices, NOC
Renewable supplySolar or other on-site generation
Rack PDUOne rack's power (needs a rack)
Rack inlet sensorOne rack's inlet temperature and humidity (needs a rack)
UPSLoad, battery, runtime, on battery or not. Set its Side (A or B)
Cooling unitSupply and return air, running or not, setpoint
Fan wallFan speed, fans running, failed and installed, airflow, pressure. Set Length m so it draws to size
GeneratorRunning or not

Mode on a UPS, cooling unit, fan wall or generator: Duty (expected to run), Standby (a spare: stopped is normal) or Maintenance (raises nothing for 8 hours, then returns to duty on its own; point at the box to see until when).

Site & limits ​

Setup, Site and limits tab. Site: Site name Northwind Data Hall, Currency MYR, Tariff per kWh 0.45, Baseline PUE 1.68, Target PUE 1.45. Limits: Inlet warning above 27, Inlet critical above 32, Escalate if still rising by 1.5 °C per 10 min, UPS battery warning below 50, UPS load warning above 90, Cooling supply air warning above 24, Clear after settled for 10 min, Reading counts as missing after 15 min. Then the heading Who hears about alerts.
Northwind's site settings
SettingWhat it changes
Site name, Currency, Tariff per kWhThe name in every page header; the cost figures on Now and Energy
Baseline PUEWhere you started. Saved vs baseline is measured against it
Target PUEThe target on Now and the wall screen, the green line on Energy, and the energy practice check
Inlet warning above (°C) / Inlet critical above (°C)The site's rack inlet limits (ASHRAE recommends 18–27 °C). A hall can override them with its own Warn above and Critical above
Escalate if still rising by (°C / 10 min)Turns a warm-hall warning critical when it keeps climbing
UPS battery warning below (%) / UPS load warning above (%)The UPS alerts
Cooling supply air warning above (°C)The "supplying warm air" alert for cooling units and fan walls
Clear after settled for (min)How long a reading must stay back in range before an alert clears
Reading counts as missing after (min)When a silent sensor or unit counts as not reporting
Who hears about alertsPush to everyone with this app; Email to the people you pick; Critical alerts only or Every alert

Questions and problems ​

PUE looks wrong, or oddly high. Check the note under PUE on Now. If there is no site meter, facility power is IT + cooling + other, which misses losses a real meter would catch, and the card says it is estimated. If not every meter in a sum is reporting, it says the figure is partial.

An alert will not clear. The unit, or the rack the alert names, has gone quiet instead of settling back into range. Silence keeps an alert open on purpose: check the device is still reporting (the Floor shows it grey, No reading).

A spare cooling unit keeps raising "stopped". Set its Mode to Standby in Setup → Devices.

A redundancy check says capacity is not entered. Enter Rated kW for each UPS and cooling unit in Setup → Devices. The check needs it to work out what is left with the largest unit out.

A device does not appear in Setup → Devices, or "Sends" is empty. Its readings are not reaching Omaya: check the gateway publishes it with the identifier registered for the device. Badges and tags are never listed.

I cannot see Setup, or Arrange on the Floor. You need configure rights on the app. Ask your administrator.

The Ask OAIA for a review button says OAIA is unavailable. AI is switched off for your organisation, or this month's allowance is used. The checks still work.

The data hall's meters also appear in Energy Monitoring. They send power readings, so Energy Monitoring lists them too. Use Data Centre for the hall, and Energy Monitoring for the rest of the building. So that Energy Monitoring's building total counts the hall once, your administrator sets the hall's meters under its site meter in Energy's Meter hierarchy, and ticks Generates power on the renewable supply meter: the solar output is then taken off the total. At Northwind the hall's meters sit under the Data hall incomer and the Rooftop solar is marked as generating.

If one side fails says set the sides. Give each UPS its Side (A or B feed) in Setup → Devices.

Make a work order is missing on a pattern. Your organisation does not have the Facility app switched on.

The wall screen says signed out. It runs as the person who opened it. Sign in again on that screen; choose an account kept for the control room so it does not depend on one person.

A page shows a "Demo data" badge. That site is a demonstration fed by a simulator, like the screenshots on this page. Your own site never shows it.

On the phone ​

Data Centre is not in the Omaya phone app, but its alerts arrive there as push notifications for everyone who has the app. The pages work in a phone's browser: Now puts the sentence and the four numbers first, every rack fits the width of the phone, and tapping a rack scrolls to its last 24 hours — so the engineer on call can take an alert with I'm on it from the phone.

Now on a phone: the menu, Right now, the green Everything is normal sentence, then the four key numbers two by two — PUE, IT load, Power and Cooling.
Now on the engineer's phone

Last updated:

Omaya platform documentation